Advice for installers

Heat pump system preparation: a guide for installers

A short, practical reference for retrofit heat pump jobs: preparing the existing system water, the commissioning checklist items that cover it, and a handover that homeowners can understand.

Water items on the HPA checklist

  • System Flushed & Cleansed (as BS 7593)
  • System purged of air
  • Inhibitor added
  • In-line filter fitted

Paraphrased layout; exact wording and source below.

The retrofit context

Most air source heat pumps in the UK are fitted to existing homes and connected to existing radiators and pipework. You will rarely be connecting to a brand-new, clean circuit. More often you are inheriting a system that has run on a boiler for years, with whatever has accumulated in it along the way: sludge, magnetite and debris.

Sludge and debris in an old system can restrict flow through radiators, pipework and the heat pump’s heat exchanger and filters. A heat pump designed to run at lower flow temperatures for longer periods depends on steady flow, so preparing the water belongs at the start of the job.

Water preparation on a retrofit job

The governing code of practice is familiar from boiler work:

BS 7593 is the British Standard code of practice for preparing, commissioning and maintaining domestic central heating and cooling water systems. It covers water treatment against scale and corrosion, cleaning and flushing of systems, and the use of in-line filters.
Source: BSI Knowledge, BS 7593(opens in a new tab)
The current version is BS 7593:2019+A1:2024. Industry guidance confirms it applies whether a system is powered by a boiler or a heat pump.
Source: ACR Journal on HHIC/HPA guidance(opens in a new tab)

BS 7593 gives you three methods to choose from, according to the system in front of you:

BS 7593 describes three cleaning and flushing methods: powerflushing (external pump and tank), mains pressure cleaning, and gravity cleaning (using the system's own circulating pump).
Source: Registered Gas Engineer summary of BS 7593:2019(opens in a new tab)

A sensible preparation sequence, in outline:

  1. Assess. Note the age and type of system, signs of sludge, and anything affecting access or drainage.
  2. Choose and explain the method. Select a BS 7593 method that suits the system and tell the homeowner which one and why.
  3. Clean and flush before connection. Remove loosened debris from the system before the heat pump is connected.
  4. Refill and treat. Refill, add inhibitor, and purge air.
  5. Filter. Fit an in-line filter to collect debris that circulates later.
  6. Check the manufacturer’s requirements. Always check the heat pump manufacturer’s installation manual and warranty terms for their water-quality requirements.
  1. STEP 1

    Old system

    Existing radiators and pipework, often holding sludge, magnetite and debris.

  2. STEP 2

    Professional clean

    Cleaned and flushed using a BS 7593 method, then refilled with treated water.

  3. STEP 3

    Filter fitted

    An in-line filter is fitted to catch debris that circulates later.

  4. STEP 4

    Heat pump connected

    Only then is the heat pump connected and commissioned.

The order matters: clean, protect, then connect.

Commissioning

Building Regulations Approved Document L (para 8.7) says heat pump heating and hot water systems should be commissioned to MCS standard MIS 3005.
Source: Registered Gas Engineer summary of BS 7593:2019(opens in a new tab)

The HPA’s published commissioning checklist for air source heat pumps gives the water preparation its own lines, which makes the work visible to the customer and to anyone who looks at the system later:

The Heat Pump Association's air source heat pump commissioning checklist asks the installer to confirm "System Flushed & Cleansed (as BS 7593)", "System purged of air", inhibitor added and an in-line filter fitted.
Source: HPA air source heat pump commissioning checklist(opens in a new tab)

Filling these in accurately, rather than ticking them by habit, is what gives the record its value. Our standards page explains each document in homeowner language, which may help when you are talking a customer through it.

Handover

A clear handover reduces call-backs and builds trust. Consider covering:

  • Which BS 7593 cleaning method was used, and that it was done before connection.
  • The inhibitor added and how its level is checked in future.
  • Where the in-line filter is and how it should be maintained.
  • How the controls work, and why warm rather than hot radiators can be normal with lower flow temperatures.
  • A copy of the completed commissioning record.
  • The manufacturer’s water-quality and servicing requirements relevant to the warranty.

What your customers are reading

Homeowners who use this site are encouraged to ask any installer how the existing system will be cleaned, which BS 7593 method will be used, and for the commissioning record. Our homeowner guide includes a question checklist, and the cleaning methods page explains the three methods without ranking them. Being ready for those questions is an easy way to stand out.

If you spot something on this site that could be clearer or more accurate, please use the contact page. Installers are also welcome to join the forum for free.

Sources

  1. F5BSI Knowledge, BS 7593 (opens in a new tab)
  2. F6ACR Journal on HHIC/HPA guidance (opens in a new tab)
  3. F7Registered Gas Engineer summary of BS 7593:2019 (opens in a new tab)
  4. F8Registered Gas Engineer summary of BS 7593:2019 (opens in a new tab)
  5. F9HPA air source heat pump commissioning checklist (opens in a new tab)

Last reviewed: . Checked against the sources listed on this page; this is not an independent technical or professional review.

Before anything is connected

Ask how your existing system will be cleaned, before the heat pump goes in.