Standards and commissioning
BS 7593, MIS 3005 and heat pump commissioning
A few documents sit behind a well-prepared heat pump installation. You do not need to read them, but knowing what each one is for helps you ask the right questions and understand what you are handed at the end.
BS 7593:2019+A1:2024
Heating water code of practice
Preparing, cleaning, flushing and treating the system water.
Approved Document L, para 8.7
Building Regulations guidance
Points heat pump commissioning to MIS 3005.
MIS 3005
MCS heat pump standard
The standard heat pump systems should be commissioned to.
BS 7593: the heating water code of practice
British Standards are published by BSI. A “code of practice” sets out recommended good practice rather than a product specification. The one that matters most for this site is BS 7593:
BS 7593 is the British Standard code of practice for preparing, commissioning and maintaining domestic central heating and cooling water systems. It covers water treatment against scale and corrosion, cleaning and flushing of systems, and the use of in-line filters.
In other words, it is the document that covers the condition of the water in your radiators and pipes: how to prepare it, clean it, protect it and keep it in good order. That is the territory this whole site is concerned with, and the reason our system cleaning guide refers to it so often.
Which version applies, and does it cover heat pumps?
Standards are revised from time to time. It is reasonable to ask which version an installer is working to. The current position, and its relevance to heat pumps, is summarised here:
The current version is BS 7593:2019+A1:2024. Industry guidance confirms it applies whether a system is powered by a boiler or a heat pump.
This point is worth underlining. BS 7593 is sometimes thought of as a “boiler” standard because it has been used alongside boiler installations for a long time. Industry guidance confirms it applies to heat pump systems too.
The cleaning methods it describes
BS 7593 does not lock installers into a single technique. It describes three:
BS 7593 describes three cleaning and flushing methods: powerflushing (external pump and tank), mains pressure cleaning, and gravity cleaning (using the system's own circulating pump).
Our cleaning methods page explains each in general terms and lists questions to ask about them.
MIS 3005 and Approved Document L
MCS is a certification scheme for small-scale renewable energy installations in the UK, including heat pumps. It publishes installation standards; the one for heat pumps is MIS 3005. Building Regulations guidance connects heat pump commissioning to it:
Building Regulations Approved Document L (para 8.7) says heat pump heating and hot water systems should be commissioned to MCS standard MIS 3005.
“Commissioning” means the set of checks, settings and records made when a system is first put into service, to confirm it has been installed and set up correctly. For a heat pump, preparing the system water is part of getting that right. For the latest details of MCS standards, go to the MCS website (opens in a new tab) rather than relying on any summary, including ours.
What a commissioning checklist looks for
Commissioning checklists turn standards into tick-boxes an installer completes and a homeowner can keep. One published checklist for air source heat pumps includes these water-related items:
The Heat Pump Association's air source heat pump commissioning checklist asks the installer to confirm "System Flushed & Cleansed (as BS 7593)", "System purged of air", inhibitor added and an in-line filter fitted.
Each of those lines connects to something on this site. “Flushed & cleansed (as BS 7593)” is the system clean. “Purged of air” means trapped air has been removed after filling. Inhibitor protects against corrosion. The in-line filter catches debris that circulates later. Definitions for all of these are in our glossary.
What this means for you
You do not need to own a copy of any standard. What helps is knowing the names, so that you can ask:
- Will my system be cleaned and flushed to BS 7593 before the heat pump is connected?
- Which of the BS 7593 methods will you use?
- Will the system be commissioned to MIS 3005?
- Will I receive the commissioning record showing cleaning, air purging, inhibitor and filter?
Always check the heat pump manufacturer’s installation manual and warranty terms for their water-quality requirements as well. The homeowner guide puts these questions into the order you are likely to need them. Installers may find the system preparation guide for installers useful as a handover aid.
Sources
- F5BSI Knowledge, BS 7593 (opens in a new tab)
- F6ACR Journal on HHIC/HPA guidance (opens in a new tab)
- F7Registered Gas Engineer summary of BS 7593:2019 (opens in a new tab)
- F8Registered Gas Engineer summary of BS 7593:2019 (opens in a new tab)
- F9HPA air source heat pump commissioning checklist (opens in a new tab)